  1. Baiji thermal power station 6 × 220 MW rehabilitation
    (ITT) com. Worked, as main subcontractor to ANSALDO energia of Italy. The main activities of the group within this contract was the following
     
    1. The camp construction for the workers
    2. Mobilization of heavy equipment
    3. Hot and cold survey of the units
    4. Blades of turbine rotors replacement
    5. Replacement of boiler tubes
    6. Many other subcontracts within the power plant

    The total contract price for the first two units (5&6) was 43 million USD while the contract price for the whole plant was 137 million USD our share was 12.2 million USD.
     
  2. The rehabilitation of Daura and Dibis gas turbine power plant
    Shamara group (ITT)
    was the main subcontractor to FIAT- AVIO of Italy for the rehabilitation of Daura gas turbine power plant 4× 37 MW and Dibis gas turbine power plant of 5× 37 MW type TG 20.

    The rehabilitation includes the following activities of the group to gather with FIAT-AVIO

    1. Camp construction
    2. Survey of all the units
    3. Blades replacement
    4. Hot path repair
    5. Bearing maintenance
    6. Main filters over haul
    7. Over haul of control system
    8. Vibration elimination of bearings
    9. Balancing of all the units
       
    The total contract price including the spear parts was 40 million USD our share was 6.2 million USD.
     
  3. Contract in Jordan singed Between ITT and Ministry of Electricity Jordan.
    Electrification of 250 villages through the construction of 132/33/11 kv transmission lines. The contract price 4 million USD.
    The contract was completed successfully.
     
  4. Yuissifiah power station 8×210 MW
    Shamara group (H.O.C) works as the main subcontractor to T.P.E. Of Russia for the construction of Yuissifiah power station on turnkey bases. The main contract price is 960 million USD divided into two phases. The work started with phase 1 for three units with a total contract price of 419 million USD.
    H.O.C main activities in the project are the following

    1. Camp construction
    2. Required personal
    3. Earth filling
    4. Piling works
    5. Concrete channels
    6. Turbine house main building
    7. Heavy equipments supply
    8. Aux. Civil contracts.
  5. Supply, install and commission of water treatment plant of 200m3 / hour to Basrah refinery total amount 1.5 million USD
     
  6. The Rehabilitation. Of Al-Haswa Power plant in Yemen. 4 unites of 840 MW each.

    AFTER LIBERATION
     
  7. H.O.C signed a 6 MW turnkey job contract in September 2003 with KBR for supply and operates diesel generators with its transformers and switchgear. Location presidential place – Baghdad amount 3.600.000 USD
     
  8. (H.O.C.) signed 9 MW turnkey job contract in October 2003 with KBR for supply and operate diesel generators with its transformers and switchgear. Location presidential place-Baghdad amount 5.430.000 USD.